Commissioned by Zhejiang Provincial Development and Reform Commission, 5 invited experts from the relevant departments, including Development and Reform Commission, finance, and environmental protection of Xiaoshan district, made the completion acceptance of the company’s precision forgings energy-saving optimization and transformation central budget investment project.
The project smoothly passed the acceptance after the on-site survey, listening to the introduction of the project situation, and reviewing the project approval, finance, and bidding etc.
With a total investment of RMB 127.09 million, the project formed the annual production capacity of 2,5239 tons of precision forging.
After completion, the project can annually save electric energy of 22.9076 million kwh, equivalent to standard coal 7,33044 tons, saving various materials of 40.6657 tons, achieving expected target of energy cascade utilization and efficient heat transfer.
Product Model | Inside Diameter | Outside Diameter | Thickness |
HM813841/10 bearing | 60.325 | 127 | 36.512 |
HM813841A/10 bearing | 60.325 | 127 | 36.512 |