With the strong support of Tri-Ring Group and the joint efforts of the whole staff involved in the construction of the Industrial Park, the first-stage construction of Tri-Ring Group & Xiangyang Industrial Park has stepped into the comprehensive ending stage.
The main part of the five plants in the first phase has been basically completed, and fully entered the construction phase of wear-resistant floor in the workshop. The pipe network for rain water, sewage and waste water within the plant area has also been basically completed, and the No.9 Landscape Road on the 9th has been fully completed while other plant roads are now in the phase of foundation construction. At present, the construction workers are devoting to the construction of the wastewater station and distribution station, so as to make adequate preparation to relocate the equipment and put them into operation.